Rehabilitación de Depuradora en la región del Lago Snagov.

Localización : Rumanía
Inicio : 15 Mayo 2007
Fin : 08 Noviembre 2009
Importe : € 4.346.223
Estado :

Overview

  The project‘s objective is the construction of a modern sewerage system in Snagov village area.

Works include:

·         Construction of approx. 18 km of 250 mm diameter, and approx. 13/4 km of 400 mm gravity sewer pipes (including twice pipe jacking across the DJ 101 B road) plus construction of new manholes and all ancillary works. The majority of this pipe laying will occur along the paved roads of Snagov and Ghermanesti villages.

·         Construction of an intermediate pumping station, together with 775 m of 180 mm diameter rising main leading to a second pumping station. Construction of this second (final) pumping station, together with 4 km of 400 mm rising main.

·         Design and construction of a new wastewater treatment plant, which shall comprise:- screening; grit removal; accumulation, mixing and pre-aeration basin coupled with primary sedimentation compartment and sand and grease trap; sewage pumping station; biological treatment module; air blowing station; excess sludge accumulation/thickening basin; thickened sludge pumping station; sludge dehydration installation; command and control module; and all ancillary works.